Skip to content
Dryside

Method

What a correct injection repair involves

Every figure on this page is one a contractor can be held to. If a quote does not match it, that is a fair question to put to whoever wrote the quote — and the answer is usually more informative than the price.

Hole diameter
13 mm
Drill angle
45°
Offset from crack
≈ ½ element thickness
Drill depth
⅔–¾ of thickness, never through
Packer spacing
150–400 mm c/c
Packers removed
24 h after injection
Re-inspection
24–48 h, and after the next rain
Silica control
On-tool extraction

11 steps, in the order they happen on site

The ordering matters as much as the content. Diagnosis is the highest-value step in the whole job and the one most often skipped, which is why it occupies the first two positions and why neither of them involves any equipment.

  1. Establish where the water is actually getting inBefore anything is drilled, the path has to be established. The crack that is visible is often not the entry point — water tracks laterally between a membrane and the concrete and exits at the weakest point, which can be metres from where it started.
  2. Rule out the things injection cannot fixBlocked ag lines, failed membranes, condensation, rising damp, leaking services, structural movement. If it is one of those, the correct outcome is to stop. This is the step most quotes skip, and it is the one that decides whether the money is well spent.
  3. Scan before drilling where the slab may be post-tensionedGround-penetrating radar and written engineer approval on any suspended or post-tensioned slab. A cut tendon is not a repairable mistake, and no schedule pressure justifies skipping it.
  4. Set out the packer positionsHoles at 150–400 mm centres, closer where the path is diffuse, and never spaced further apart than the element is thick.
  5. Drill at 45 degrees, offset from the crack13 mm holes, offset from the crack line by roughly half the element thickness so the hole intersects the crack at depth, drilled to two-thirds or three-quarters of the thickness. Never straight through — a hole that exits the far face gives the resin somewhere to escape and gives the water a new path.
  6. Flush the holes with waterThis does two jobs: it proves the packers are connected to each other through the crack, and it pre-wets the crack, which a water-reactive polyurethane needs in order to cure properly.
  7. Fit mechanical packersSteel or alloy packers set into the drilled holes, which take injection pressure. Surface ports glued to the face will not adhere to a wet wall, which is why cheap wet-wall repairs fail.
  8. Kill heavy flow firstWhere water is running rather than weeping, a hydraulic plug or oakum goes in first so the resin is not simply washed out before it can react.
  9. Inject bottom to topStarting at the lowest packer and moving up only when resin shows at the packer above. That confirms the crack is filling continuously rather than the resin finding one easy path.
  10. Leave the packers in for 24 hoursThen cut back, remove them, and make good. Cutting the packers off the same day is how it emerges later that the resin had not finished doing its job.
  11. Re-inspect after rainRe-inspection after 24–48 hours and after the next real rain event, photographed from the same positions as the before shots so the change is measurable rather than remembered.

Pressure bands

Pressure is chosen for the element, not for the machine. Too little and the resin never reaches the far side of the crack; too much and the crack widens, mortar beds blow out, or a thin slab lifts.

ApplicationTypical pressureWhat over-pressure looks like
Epoxy through bonded surface ports0.7–3.5 barPorts popping off the face, resin bleeding out around the seal
Polyurethane through mechanical packers35–140 barResin appearing far from the crack, the crack visibly widening
Acrylate gel, curtain injection2–15 barGround heave, gel surfacing away from the wall — soil is being fractured rather than permeated
Core-filled block retaining wallWell below concrete pressuresMortar beds blowing out — stop immediately, the wall has been made worse

What the record should look like afterwards

At minimum: photographs, and a written description of what was found and what was done about it. Before and after shots taken from the same positions are genuinely comparable; two pictures of roughly the same wall are not, and the difference only becomes apparent when there is an argument about whether anything changed.

On larger commercial work the standard goes further — a numbered packer map, resin batch numbers, and the volume injected at each point. That is real work to produce and it is not standard on domestic jobs, so where an engineer or a body corporate requires it, it belongs in the scope at tender stage rather than being assumed and argued about later.

The one item worth insisting on regardless of job size is a re-inspection after rain, agreed in writing before the work starts. A repair that has not seen water has not been tested.

Safety, stated plainly

  • Confined spaces. Lift pits, tanks and some plant rooms are confined spaces under AS 2865. That means a permit, atmospheric testing, a standby person and a rescue plan — typically $800–$2,000 a day, which should be itemised on a quote rather than hidden in a rate.
  • Silica dust. Drilling concrete generates respirable crystalline silica, with a workplace exposure standard of 0.05 mg/m³. On-tool extraction or wet drilling, every time, and worse in an enclosed basement where the dust has nowhere to go.
  • Isocyanates. Uncured polyurethane resins contain them and sensitisation is permanent. People should be kept out of the immediate work area during injection, and the safety data sheet for every product used is something a property owner is entitled to ask for.

When a competent contractor should refuse

There are situations where the correct professional answer is to decline the work: a designed movement joint, a wall that is still moving, a slab that has not been scanned, or a crack where the real problem is drainage. None of those are fixed by resin, and injecting them makes the eventual repair harder.

A negative-side seal also should not be described as making a basement permanently dry, because sealing redirects water rather than removing it. That distinction is the single most common source of dispute after an otherwise competent repair, and it is why the redirection risk belongs in writing before the work, not in a warranty argument afterwards.

Common questions

Why are the holes drilled at an angle instead of straight at the crack?
Because the seal has to sit inside the wall, not on its face. A hole drilled at 45 degrees and offset from the crack line by roughly half the element thickness meets the crack plane at about mid-depth, so the resin fills the crack through the body of the concrete where the water pressure is. A hole drilled straight at the crack from the face reaches it at the surface, where a seal is simply pushed off by the head behind it. On a 250 mm wall that means starting the hole about 125 mm to one side, alternating left and right in a stitch pattern.
How can anyone tell whether the crack actually filled?
Two ways, and both should be in the scope. The first is travel confirmed during injection: resin appearing at the next packer along is direct evidence it moved through the crack rather than sitting in the hole, which is the entire reason for injecting from the bottom up and only moving on when the packer above shows resin. The second is observation over time — a minimum of 24 to 48 hours, and where the programme allows it, through a genuine rain event. A repair signed off the same afternoon has not been verified, it has been finished.
What does packer spacing have to do with whether the repair holds?
Spacing decides how far resin has to travel through a crack that narrows as it goes. The rule is that spacing should never exceed the element thickness. Packers set at 600 mm centres on a 200 mm wall ask the resin to travel three times the wall thickness, and it will not get there, so the wall leaks between the packers. It is a simple rule and it is broken constantly, because wider spacing means fewer holes and a cheaper-looking quote.
Is there a written record at the end of a properly run job?
There should be, and the standard varies. The minimum worth accepting is photographs taken from fixed positions before and after, plus a written description of what was found and what was done about it. On larger commercial work the record extends to a numbered packer map with resin batch numbers and the volume injected at each point. That level of documentation is not standard on domestic work and it costs money to produce, so if an engineer or a body corporate requires it, it belongs in the scope at tender rather than being assumed.
What should a confined space add to a quote?
Lift pits, tanks, sumps and many basement plant rooms meet the definition of a confined space under AS 2865. Entry legally requires a written permit, atmospheric testing before and during entry, a standby person stationed outside who produces no work at all, a means of communication and a rescue plan with equipment on site. That typically adds $800 to $2,000 a day. A lift pit quote with no such line in it is either not accounting for the requirement or not planning to meet it.

Comparing quotes against this method

Asking each contractor to price against the method above is the only reliable way to make three numbers comparable. Where a quote departs from it, the reason is worth hearing — sometimes there is a good one.

Working out what the problem is first — fifteen situations where injection is the wrong repair

Contact a licensed waterproofer